SCWA Drops Turbine Proposal at Laurel Lake

Decision "strictly economics," according to Suffolk County Water Authority chairman.

A 150-foot wind turbine proposed for the that had locals up in arms over the winter will not move forward, according to a Newsday article.

In January, neighbors largely disapproved of the proposal - put forth by the Suffolk County Water Authority - at a public hearing at .

A financial analysis concluded that the $500,000 turbine, which the , would take 20 years to pay off, leading to doubts about how worthwhile the proposal was.

Find out what's happening in North Forkwith free, real-time updates from Patch.

The report quotes SCWA Board Chairman James Gaughran as saying the following: "Our original estimate was that the payback period would be at most 12 years. Now we're being told it will be 20 years or even more."

Click here to read the entire article on Newsday.

Find out what's happening in North Forkwith free, real-time updates from Patch.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here